| APP ID : | 200144 |
| APP Code : | UDCGP
|
| Financial Year : | 2023-2024 |
| Budget Type : | Development |
| Project Name : | Urban Development and City Governance Project |
| Procuring Entity : | Goutam Prasad Chowdhury |
| District : | Cumilla |
| Procurement Nature | Works |
| Type of Emergency | Normal |
| Package No | UDCGP-CuCC-D-2 |
| Package Description | Construction of RCC Drain from Cumilla Chittagong Bypass Road to west side along the main road. |
| Lot No. | Lot Description | Qty | Unit | Estimated Cost (In BDT) |
| 01 | Construction of RCC Drain from Cumilla Chittagong Bypass Road to west side along the main road. | 1.00 | Nos | 82410000.00 |
|
| Package Estimated Cost (In BDT) | 82410000.00 |
| Category | Construction work; Site preparation work; Building demolition and wrecking work and earthmoving work; Test drilling and boring work; Works for complete or part construction and civil engineering work; Building construction work; Engineering works and construction works; Construction work for pipelines, communication and power lines, for highways, roads, airfields and railways; flatwork; Construction work for water projects; Construction works for plants, mining and manufacturing and for buildings relating to the oil and gas industry; Roof works and other special trade construction works; Building installation work; Electrical installation work; Insulation work; Plumbing and sanitary works; Fencing, railing and safety equipment installation work; Mechanical installations; Building completion work; Plastering work; Joinery and carpentry installation work; Floor and wall covering work; Painting and glazing work; Other building completion work; Hire of construction and civil engineering machinery and equipment with operator; Hire of cranes with operator; Hire of earthmoving equipment with operator |
| Approving Authority | PD |
| PQ Requires | No |
| Procurement Method | Open Tendering Method |
| Procurement Type | NCT |
| Package Type | e-GP |
| Source of Fund | Aid or Grant |
| Development Partners | Japan International Cooperation agency(JICA) |
| Expected Date of Advertisement of Tender on e-GP website | 19-Nov-2023 |
| Expected Date of submission of Tender | 17-Dec-2023 |
| Expected Date of Opening of Tender | 17-Dec-2023 |
| Expected Date of Submission of Evaluation Report | 31-Dec-2023 |
| Expected Date of Approval for Award of Contract | 07-Jan-2024 |
| Expected Date of Issuance of the NOA | 14-Jan-2024 |
| Expected Date of Signing of Contract | 28-Jan-2024 |
| Expected Date of Completion of Contract | 27-Jan-2025 |
| Total Time to Contract Signing | 70 |